Current delivery times for standard products

(ex works central factories in Germany and France)

General information

Data status: July 11th, 2022

A weekly update takes place.

The times given in the following tables are to be understood as non-binding guideline values. The specific times at the level of individual order items may vary from this depending on the individual technical configuration of the product ordered.

Gear unit

Fermer tableau
Product group and type Current standard delivery time (non-binding!) ex works factory for new orders Existing orders scheduled until 30.09.2022:
Expected delivery delay (non-binding!) compared to confirmed delivery date
(If not otherwise stated: There's currently no reliable information on delivery delays for orders with later confirmed delivery date.)
Helical gear unit
R..07 11 weeks  
R..17 11 weeks  
R..27 11 weeks  
R..37 11 weeks  
R..47 11 weeks  
R..57 11 weeks  
R..67 2 weeks  
R..77 2 weeks  
R..87 2 weeks  
R..97 2 weeks  
R..107 2 weeks  
R..127 2 weeks  
R..137 1 weeks  
R..147 1 week  
R..167 1 week  
 
Helical-worm gear unit
S..37 2 weeks  
S..47 2 weeks  
S..57 2 weeks  
S..67 6 weeks  
S..77 2 weeks  
S..87 2 weeks  
S..97 2 weeks  
 
Helical-bevel gear unit
K..37 2 weeks
i=4,125 - 10 weeks
 
K..47 2 weeks
i=4,125 - 10 weeks
 
K..57 10 weeks  
K..67 20 weeks  
K..77 14 weeks  
K..87 10 weeks  
K..97 10 weeks  
K..107 10 weeks  
K127 1 week  
K157 1 week  
K167 1 week  
K187 1 week  
K..19 2 weeks  
K..29 2 weeks  
K..39 (except KA39) 10 weeks  
KA39 10 weeks  
K..49 2 weeks  
KA49 10 weeks
KA / KAF / KF / KT / KH
 
 
Parallel-shaft helical gear unit
F..27 2 weeks  
F..37 2 weeks  
F..47 2 weeks  
F..57 2 weeks  
F..67 2 weeks  
F..77 2 weeks  
F..87 2 weeks  
F..97 2 weeks  
F..107 2 weeks  
F127 1 week  
F157 1 week  
 
Spiroplan gear unit
W..10 2 weeks  
W..20 6 weeks  
W..30 6 weeks  
W..37 6 weeks  
W..47 6 weeks  
W..19 8 weeks  
W..29 5 weeks  
W..39 5 weeks  
W..49 5 weeks  
 
Adapter
AM/AMS/AQ/AQS/AT/AR/AD 2 weeks  
 
Variable speed gear unit VARIBLOC®
VU/VZ 01 - 51 2 weeks  
 
Variable speed gear unit VARIMOT®
D16 - 46 2 weeks  
 
Trolley Drives
HS 40 2 weeks  
HS 50 2 weeks  
HS 60 6 weeks  
HK 30 2 weeks  
HK 40 2 weeks  
HK 50 10 weeks  
HK 60 20 weeks  
HW30 6 weeks  
 
Stainless steel Gear unit and Gearmotor
RESF37 8 weeks  
KES37 without motor 2 weeks  
KES37 (TENV78 - 4 B) 2 weeks  
 
Planetary gear unit
BS202 1 week  
BS302 1 week  
BS402 1 week  
BS502 1 week  
BS602 1 week  
BS802 8 weeks  
     
PSF120 1 week  
PSF220 1 week  
PSF320 1 week  
PSF520 1 week  
PSF620 1 week  
PSF720 2 weeks  
PSF820 2 weeks  
PSF920 2 weeks  
     
PSC220 1 week  
PSC320 1 week  
PSC420 1 week  
PSC520 1 week  
PSC620 1 week  
     
PxG BG2 1 week  
PxG BG3 1 week  
PxG BG4 1 week  
PxG BG5 1 week  
PxG BG6 2 weeks  
PxG BG7 2 weeks  
     
Special ratios, special shafts SK applications, as well as OS - paint on request  
Nous avons déposé ici un tableau pour votre usage.

Industrial Gear

Fermer tableau
Product group and type Current standard delivery time (non-binding!) ex works factory for new orders Existing orders scheduled until 30.09.2022:
Expected delivery delay (non-binding!) compared to confirmed delivery date
(If not otherwise stated: There's currently no reliable information on delivery delays for orders with later confirmed delivery date.)
MC-series on request  
P-series on request
X-series on request  
XP-series on request  
Nous avons déposé ici un tableau pour votre usage.

Motor

Fermer tableau
Product group and type Current standard delivery time (non-binding!) ex works factory for new orders Existing orders scheduled until 30.09.2022:
Expected delivery delay (non-binding!) compared to confirmed delivery date
(If not otherwise stated: There's currently no reliable information on delivery delays for orders with later confirmed delivery date.)
Asynchronous-Motor without special parts
DR2S 56 6 weeks  
DR/DRN/DR2S 63 4 weeks  
DRN/DR2S 71 4 weeks  
DRN/DR2S 80 4 weeks  
DR/DRN 90 7 weeks  
DR/DRN 100 7 weeks  
DR/DRN 112 7 weeks  
DR/DRN 132S - 132M 7 weeks  
D..132L 2 weeks  
D..160 8 weeks  
D..180 8 weeks  
D..200 2 weeks  
D..225 2 weeks  
D..250 2 weeks 1 weeks
D..280 2 weeks 1 weeks
D..315 2 weeks 1 weeks
DRN355 approx. 20 weeks  
 
Asynchronous-Motor with special parts
D..132L on request  
D..160 on request  
D..180 on request  
D..200 on request  
D..225 on request  
D..250 on request  
D..315 on request  
 
Torque motors
MT/MV132ML - 160M on request  
DRM 71-132 7 weeks  
DR2M 71 7 weeks  
 
Asynchronous servo motor
CT/CV132M - 200L on request  
DRL (71-132) 7 weeks  
DRL (160-225) 2 weeks  
DR2L (71-80) 7 weeks  


 
DRU71 - 100 7 weeks  
DAS80 - 100 7 weeks  
DT/DV/CT71 - 132S 7 weeks  
 
Servo motor
CM71 2 weeks  
CM90 2 weeks  
CM 112 (S/M/L) 2 weeks  
     
CMP40 2 weeks  
CMP50 2 weeks  
CMP63 2 weeks  
CMP71 2 weeks  
CMP 80 2 weeks  
CMP 100 2 weeks  
CMP112S / M / L 2 weeks  
CMP112E / H on request  
     
CM3C63 2 weeks  
CM3C71 2 weeks  
CM3C80 2 weeks  
CM3C100 2 weeks  
     
CMS / PGT 2 weeks  
CMS63/M/BP KGT 200mm on request  
CMSMB on request  
     
CMD55 - 138 on request  
 
Servo linear motor
SL2 on request  
 
Asynchronous linear motor
DLD on request  
 
Elektronics motor DRC..
DRC1, 2, 3, 4 2 weeks  
 
Purchased motors
Flameproof EX motors > 10 weeks  
AC motors (large 2p, 6p and PU) 9 weeks  
Nous avons déposé ici un tableau pour votre usage.

Gearmotor, MOVIGEAR, etc.

Fermer tableau
Product group and type Current standard delivery time (non-binding!) ex works factory for new orders Existing orders scheduled until 30.09.2022:
Expected delivery delay (non-binding!) compared to confirmed delivery date
(If not otherwise stated: There's currently no reliable information on delivery delays for orders with later confirmed delivery date.)
Gearmotor
Gear unit with asynchronous motor The largest relevant value from the tables for gear unit and asynchronous motor applies,
plus 3 working days lead time for the entire unit.
 
Gear unit with servo motor The largest relevant value from the tables for gear unit and servo motor applies,
plus 3 working days lead time for the entire unit.
 
 
MOVI-C® / Gearmotor/Motor with digital data interface MOVILINK® DDI
../DI 31 weeks

If table value for gear unit or motor is larger: The largest value applies, plus 3 working days lead time for the entire unit.
16 weeks
 
Gearmotor/Motor with encoder
… /AZ1Z 7 weeks

If table value for gear unit or motor is larger: The largest value applies, plus 3 working days lead time for the entire unit.
 
… /AZ2Z 7 weeks

If table value for gear unit or motor is larger: The largest value applies, plus 3 working days lead time for the entire unit.
 
… /EZ2Z 7 weeks

If table value for gear unit or motor is larger: The largest value applies, plus 3 working days lead time for the entire unit.
 
 
Gearmotor/Motor with inverter MOVIMOT® D
.. /MM The largest relevant value from the tables for gear unit, asynchronous motor and MOVIMOT® D for motor mounting applies, plus 3 working days lead time for the entire unit.  
 
Gearmotor/Motor with motor starter MOVI-SWITCH®
.. /MSW The largest relevant value from the tables for gear unit, asynchronous motor and MOVI-SWITCH® applies, plus 3 working days lead time for the entire unit.  
 
MOVI-C® / Gearmotor/Motor with inverter MOVIMOT® advanced
.../DAC
(Direct AS-Interface Communication)
The largest relevant value from the tables for gear unit, asynchronous motor and MOVI-C® electronics cover applies, plus 3 working days lead time for the entire unit.  
.../DBC
(Direct Binary Communication)
The largest relevant value from the tables for gear unit, asynchronous motor and MOVI-C® electronics cover ../DBC applies, plus 3 working days lead time for the entire unit.  
.../DSI
(Direct Systembus Installation)
The largest relevant value from the tables for gear unit, asynchronous motor and MOVI-C® electronics cover ../DSI applies, plus 3 working days lead time for the entire unit.  
.../DFC
(Direct Fieldbus Communication)
The largest relevant value from the tables for gear unit, asynchronous motor and MOVI-C® electronics cover ../DFC applies, plus 3 working days lead time for the entire unit.  
 
MOVI-C® / Drive system MOVIMOT® performance
"...CM3C80…/DAC
(Direct AS-Interface Communication)"
The largest relevant value from the tables for gear unit, servo motor CM3C80 and MOVI-C® electronics cover applies, plus 3 working days lead time for the entire unit.  
"...CM3C80.../DBC
(Direct Binary Communication)"
The largest relevant value from the tables for gear unit, servo motor CM3C80 and MOVI-C® electronics cover applies, plus 3 working days lead time for the entire unit  
"...CM3C80.../DSI
(Direct Systembus Installation)"
The largest relevant value from the tables for gear unit, servo motor CM3C80 and MOVI-C® electronics cover applies, plus 3 working days lead time for the entire unit.  
"...CM3C80…/DFC
(Direct Fieldbus Communication)"
The largest relevant value from the tables for gear unit, servo motor CM3C80 and MOVI-C® electronics cover applies, plus 3 working days lead time for the entire unit.  
 
Drive unit MOVIGEAR® Gen. B
MGF...DSM 2 weeks  
 
Drive system MOVIGEAR® Gen. B
"MGF…-DAC-B
(Direct AS-Interface Communication)"
2 weeks  
"MGF…-DBC-B
(Direct Binary Communication)"
2 weeks  
"MGF…-DSC-B
(Direct SBus Communication)"
6 weeks  
"MGF…-SNI-B
(Single Line Network Installation)"
6 weeks  
 
MOVI-C® / Drive unit MOVIGEAR® classic
MGF…-DSM-C 2 weeks  
 
MOVI-C® / Drive system MOVIGEAR® performance
"MGF…-DAC-C
(Direct AS-Interface Communication)"
26 weeks 25 weeks
"MGF…-DBC-C
(Direct Binary Communication)"
26 weeks 25 weeks
"MGF…-DSI-C
(Direct Systembus Installation)"
26 weeks 25 weeks
"MGF…-DFC-C
(Direct Fieldbus Communication)"
26 weeks 25 weeks
 
Compact extra low voltage drives
F03 (… DCA) 1 week  
W03 (… DCA) 1 week  
KNZ ... DCA 1 week  
PNZ ... DCA 1 week  
 
Drive system for light-duty materials handling technology
ECDriveS®    
Nous avons déposé ici un tableau pour votre usage.

Elektronics

Fermer tableau
Product group and type Current standard delivery time (non-binding!) ex works factory for new orders Existing orders scheduled until 30.09.2022:
Expected delivery delay (non-binding!) compared to confirmed delivery date
(If not otherwise stated: There's currently no reliable information on delivery delays for orders with later confirmed delivery date.)
Standard-Inverter MOVITRAC® B
(voltage supply VAC: 1x 200/240) - basic unit
MC 07B size 0XS (0,25 - 0,37 kW) 11 weeks 8 weeks
MC 07B size 0S (0,55 - 0,75 kW) 14 weeks 8 weeks
MC 07B size 0L (1,1 - 2,2 kW) 1 week  
 
Standard-Inverter MOVITRAC® B
(voltage supply VAC: 3x 200/240) - basic unit
MC 07B size 0XS (0,25 - 0,37 kW) 1 weeks
Quantity>5; 12
1 week
MC 07B size 0S (0,55 - 0,75 kW) 1 weeks
Quantity>5; 12
1 week
MC 07B size 0L (1,1 - 2,2 kW) 1 weeks 1 week
MC 07B size I (3,7 kW) 23 weeks 15 weeks
MC 07B size II (5,5 - 7,5 kW) 17 weeks 19 weeks
MC 07B size III (11 - 15 kW) 25 weeks 10 weeks
MC 07B size IV (22 - 30 kW) 19 weeks 11 weeks
 
Standard-Inverter MOVITRAC® B
(voltage supply VAC: 3x 400/500) - basic unit
MC 07B size 0XS (0,25 - 0,37 kW) 6 weeks 2 weeks
MC 07B size 0S (0,55 - 1,5 kW) 18 weeks 8 weeks
MC 07B size 0L (2,2 - 4 kW) 18 weeks 10 weeks
MC 07B size IIS (5,5 - 7,5 kW) 21 weeks 12 weeks
MC 07B size II (11 kW) 17 weeks 19 weeks
MC 07B size III (15 - 30 kW) 25 weeks 10 weeks
MC 07B size IV (37 - 45 kW) 19 weeks 11 weeks
MC 07B size V (55 - 75 kW) 16 weeks 10 week
 
Standard-Inverter MOVITRAC® B with ...
Field bus connection DFE.. 13 weeks
respectively the above mentioned time for the basic unit (if longer)
19 weeks
Field bus connection DFP.. 13 weeks
respectively the above mentioned time for the basic unit (if longer)
 
Field bus connection DFD.. 13 weeks
respectively the above mentioned time for the basic unit (if longer)
 
 
Application inverter MOVIDRIVE® B
(voltage supply VAC: 3x 200 - 240) - basic unit
MOVIDRIVE size I (1,5 - 3,7 kW) 23 weeks 15 weeks
MOVIDRIVE size II (5,5 - 7,5 kW) 17 weeks 19 weeks
MOVIDRIVE size III (11 - 15 kW) 25 weeks 10 weeks
MOVIDRIVE size IV (22 - 30 kW) 19 weeks 11 weeks
 
Application inverter MOVIDRIVE® B
(voltage supply VAC: 3x 380 - 500) - basic unit
MOVIDRIVE size 0 (0,55 - 1,5 kW) 15 weeks 19 weeks
MOVIDRIVE size I (1,5 - 4 kW) 23 weeks 15 weeks
MOVIDRIVE size IIS (7,5 - 11 kW) 21 weeks 12 weeks
MOVIDRIVE size II (11 kW) 17 weeks 19 weeks
MOVIDRIVE size III (15 - 30 kW) 25 weeks 10 weeks
MOVIDRIVE size IV (37 - 45 kW) 19 weeks 11 weeks
MOVIDRIVE size V (55 -75 kW) 16 weeks 10 weeks
MOVIDRIVE size VI (90 - 132 kW) 8 weeks 18 weeks
MOVIDRIVE size VII (160 - 315 kW) 1 weeks 3 weeks
 
Application-Inverter MOVIDRIVE® B with ...
Field bus interface DFE.. 13 weeks
respectively the above mentioned time for the basic unit (if longer)
19 weeks
Field bus interface DFP.. 13 weeks
respectively the above mentioned time for the basic unit (if longer)
 
Field bus interface DFC../DFD.. 13 weeks
respectively the above mentioned time for the basic unit (if longer)
 
Field bus interface DFI.. 13 weeks
respectively the above mentioned time for the basic unit (if longer)
 
Field bus interface DFS.. 13 weeks
respectively the above mentioned time for the basic unit (if longer)
19 weeks
Encoder interface DEH11B 13 weeks
respectively the above mentioned time for the basic unit (if longer)
 
Encoder interface DER11B 13 weeks
respectively the above mentioned time for the basic unit (if longer)
 
Encoder interface DEH21B 13 weeks
respectively the above mentioned time for the basic unit (if longer)
 
Encoder interface DEU21B 13 weeks
respectively the above mentioned time for the basic unit (if longer)
 
Encoder interface DIP11A 13 weeks
respectively the above mentioned time for the basic unit (if longer)
 
Encoder interface DIP11B 13 weeks
respectively the above mentioned time for the basic unit (if longer)
 
 
Regenerative power supply MOVIDRIVE® B
MDR size II (15 kW) 17 weeks 17 weeks
MDR size III (37 kW) 25 weeks 10 weeks
MDR size IV (75 kW) 19 weeks 11 weeks
MDR size VI (132 - 160 kW) 8 weeks 18 weeks
MDR size VII (160 - 315 kW) 1 weeks 3 weeks
 
Multi-axis servo inverter MOVIAXIS®
Axis module MXA - A size I (2 - 8 A) 13 weeks  
Axis module MXA - A size II (12 - 16 A) 13 weeks  
Axis module MXA - A size III (24 - 32 A) 2 weeks  
Axis module MXA - A size IV (48 A) 12 weeks  
Axis module MXA - A size V (64 A) 5 weeks  
Axis module MXA - A size VI (100 A) 2 weeks  
Supply module MXP 10 weeks  
Supply and regenerative module MXR 10 weeks  
 
Simple-Inverter MOVITRAC® LTE
MOVITRAC® LTE on request  
 
Standard-Inverter MOVITRAC® LTP
MOVITRAC® LTP on request  
 
Decentralized installation: Standard inverter MOVIMOT®
MOVIMOT® D size I for motor mounting 2 weeks  
MOVIMOT® D size II for motor mounting 3 weeks  
Movimot D mounted next to the motor 10 weeks  
Circuit board connection Movimot size 1 3 weeks  
any MOVIMOT® D with fieldbus connection MFE52./62. 10 weeks 12 weeks
 
Dezentralized installation: Motor starter MOVI-SWITCH®
MSW 3 weeks  
 
Dezentralized installation: Feld distributor MF../Z.
MF... / Z.1A 9 weeks 8 weeks
MF... / Z.3A 9 weeks 8 weeks
MF... / Z.6A 12 weeks 11 weeks
MF... / Z.7A 12 weeks 11 weeks
MF... / MM D size I / Z.8A 10 weeks 9 weeks
MF... / MM D size II / Z.8A 10 weeks 9 weeks
any field distributors …/Z. with fieldbus connection MFE52./62. / 10 weeks 10 weeks
 
Dezentralized installation: Distributor resp. inverter MOVIFIT®
MOVIFIT MTA 7 weeks 10 weeks
MOVIFIT MTS 6 weeks 5 weeks
MOVIFIT MTF1 20 weeks 9 weeks
MOVIFIT MTF2 19 weeks 5 weeks
MOVIFIT MTM 5 weeks 5 weeks
MOVIFIT Compact 2 weeks  
 
Dezentralized installation: Inverter MOVIPRO®
MOVIPRO® 19 weeks 17 weeks
 
Wall mounting: Simple inverter MOVI4R-U®
MOVI4R-U 2 weeks  
 
Contactless energy transfer MOVITRANS®
THM 14 weeks  
MOVITRANS® on request  
 
SNI Controller
SNI Controller A-Box 9 weeks 7 weeks
SNI Controller E-Box 3 weeks  
 
MOVI-C® / Standard-Inverter MOVITRAC® advanced (voltage supply VAC: 1x 200 - 240) - basic unit
MCX9.0A size 0S (1,7 - 4,2 A) 31 weeks 22 weeks
MCX9.0A size 0L (5,5 - 11 A) 31 weeks 22 weeks
 
MOVI-C® / Standard-Inverter MOVITRAC® advanced (voltage supply VAC: 3x 200 - 240) - basic unit
MCX9.0A size 0S (1,7 - 5,5 A) 31 weeks 22 weeks
MCX9.0A size 0L (7 - 14 A) 31 weeks 22 weeks
MCX9.0A size III (21,3 A) 31 weeks 22 weeks
MCX9.0A size IV (29 - 42 A) 31 weeks 22 weeks
MCX9.0A size V (57 - 84 A) 31 weeks 22 weeks
MCX9.0A size VI (108 A) 31 weeks 22 weeks
 
MOVI-C® / Standard-Inverter MOVITRAC® advanced (voltage supply VAC: 3x 380 - 500) - basic unit
MCX9.0A size 0S (1 - 5,5 A) 31 weeks 22 weeks
MCX9.0A size 0L (7 - 16 A) 31 weeks 22 weeks
MCX9.0A size III (24 A) 31 weeks 22 weeks
MCX9.0A size IV (32 - 46 A) 31 weeks 22 weeks
MCX9.0A size V (62 - 91 A) 31 weeks 22 weeks
MCX9.0A size VI (113 - 177 A) 31 weeks 22 weeks
 
MOVI-C® / Application inverter MOVIDRIVE® technology (voltage supply VAC: 3x 200 - 240) - basic unit
MDX9.A size II (7 - 9,3 A) 28 weeks 13 weeks
MDX9.A size III (14 A) 27 weeks 7 weeks
MDX9.A size IV (21,3 - 29 A) 28 weeks 9 weeks
MDX9.A size V (42 - 57A) 27 weeks 18 weeks
MDX9.A size VI (84 - 108A) 11 weeks 7 weeks
 
MOVI-C® / Application inverter MOVIDRIVE® technology (voltage supply VAC: 3x 380 - 500) - basic unit
MDX9.A size I (2 - 4 A) 30 weeks 8 weeks
MDX9.A size II (5,5 - 9,5 A) 28 weeks 13 weeks
MDX9.A size III (12,5 - 16 A) 27 weeks 7 weeks
MDX9.A size IV (24 - 32 A) 28 weeks 9 weeks
MDX9.A size V (46 - 75A) 27 weeks 18 weeks
MDX9.A size VI (91 - 149A) 11 weeks 7 weeks
MDX9.A size VII (177 - 300A) 2 weeks  
 
MOVI-C® / Application inverter MOVIDRIVE® technology with...
Field bus interface CFN..
(PROFINET)
9 weeks
respectively the above mentioned time for the basic unit (if longer)
 
Field bus interface CFE..
(EtherNet/IPTM and Modbus TCP)
9 weeks
respectively the above mentioned time for the basic unit (if longer)
 
Field bus interface CFP..
(PROFIBUS)
5 weeks
respectively the above mentioned time for the basic unit (if longer)
 
Field bus interface CFL..
(POWERLINK)
5 weeks
respectively the above mentioned time for the basic unit (if longer)
 
 
MOVI-C® / Application inverter MOVIDRIVE® system (voltage supply VAC: 3x 200 - 240) - basic unit
MDX9.A size II (7 - 9,3 A) 28 weeks 13 weeks
MDX9.A size III (14 A) 27 weeks 7 weeks
MDX9.A size IV (21,3 - 29 A) 28 weeks 9 weeks
MDX9.A size V (42 - 57A) 27 weeks 18 weeks
MDX9.A size VI (84 - 108A) 11 weeks 7 weeks
 
MOVI-C® / Application inverter MOVIDRIVE® system (voltage supply VAC: 3x 380 - 500) - basic unit
MDX9.A size I (2 - 4 A) 30 weeks 8 weeks
MDX9.A size II (5,5 - 9,5 A) 28 weeks 13 weeks
MDX9.A size III (12,5 - 16 A) 27 weeks 7 weeks
MDX9.A size IV (24 - 32 A) 28 weeks 9 weeks
MDX9.A size V (46 - 75A) 27 weeks 18 weeks
MDX9.A size VI (91 - 149A) 11 weeks 7 weeks
MDX9.A size VII (177 - 300A) 2 weeks  
 
MOVI-C® / Application inverter MOVIDRIVE® modular
single axis module
MDA size I (2 - 12 A) 40 weeks 21 weeks
MDA size II (16 - 24 A) 28 weeks 21 weeks
MDA size III (32 - 48 A) 25 weeks 17 weeks
MDA size IV (64 A) 29 weeks 19 weeks
MDA size V (100 A) 27 weeks 15 weeks
MDA size VI (140 - 180 A) 13 weeks 13 weeks
 
MOVI-C® / Application inverter MOVIDRIVE® modular double axis module
MDD size I (2x 2 - 2x 4 A) 28 weeks 19 weeks
MDD size II (2x 2 - 2x 8 A) 17 weeks 19 weeks
 
MOVI-C® / Application inverter MOVIDRIVE® modular supply module
MDP size I & IA (10 kW) 20 weeks 16 weeks
MDP size II (25 kW) 15 weeks 19 weeks
MDP size III (50-75 kW) 14 weeks 20 weeks
MDP size IV (110 kW) 8 weeks 17 weeks
 
MOVI-C® / Application inverter MOVIDRIVE® modular regenerative power supply module
MDR9.A size IV (50-75 kW) 8 weeks  
 
MOVI-C® Controller
UHX25A Controller standard 6 weeks 1 weeks
UHX45A Controller advanced 12 weeks 5 weeks
UHX65A Controller progressive 28 weeks 20 weeks
UHX85A Controller power 2 weeks 7 weeks

MOVI-C® Fieldcontroller
FHX25A Fieldcontroller standard 3 weeks  
FHX45A Fieldcontroller advanced 3 weeks  
 
MOVI-C® / Decentralized inverter MOVIMOT flexible
MMF…/DAC
(Direct AS-Interface Communication)
27 weeks 27 weeks
MMF…/DBC
(Direct Binary Communication)
27 weeks 27 weeks
MMF…/DSI
(Direct Systembus Installation)
27 weeks 27 weeks
MMF…/DFC
(Direct Fieldbus Communication)
27 weeks 27 weeks
 
MOVI-C®  / Electronics cover (for MOVIMOT advanced, MOVIMOT performance, MOVIGEAR)
…DAC
(Direct AS-Interface Communication)"
26 weeks 25 weeks
…DBC
(Direct Binary Communication)
26 weeks 25 weeks
…DSI
(Direct Systembus Installation)
26 weeks 25 weeks
…DFC
(Direct Fieldbus Communication)
26 weeks 25 weeks
 
Cable
Encoder cable 11 weeks  
Motor cable 17 weeks  
Hybrid cable 10 weeks  
Special cable 24 weeks  
DDI cable 5 weeks  
Purchase cable on request  
Koax cable 3 weeks  